Campus Wired Network Project

MTSU Network Services is continually updating the campus wired network. Projects include expanding the inter-building fiber network, adding additional port connectivity in specific buildings, and upgrading older equipment no longer capable of supporting the demand for more bandwidth and security. Each year, TAF and ITD fund upgrades on selected buildings that need network improvements. Over the last two years there has also been major changes to the core network by adding network electronics that work together to create redundant building connectivity with 40Gbps interconnections. The wireless core network was also upgraded in anticipation of additional wireless traffic generated by the expansion of wireless networking in all campus buildings.

       
       
 

Academic / Administrative

 

$16,059,162

       

 

 Upgrades from FY2016 still in progress

   
Date of Upgrade Building Status cost
Fall 2016 Davis Science Building In Progress $340,501
Fall 2016 Wiser-Patten Science In Progress $394,243
 

TOTAL FY2016

 

$ 734,744

       

 

Current Upgrades for FY2017

   
Date of Upgrade Building Status cost
Summer 2016 Alumni Memorial Gym  Complete $202,000
 Summer 2016 Boutwell Dramatic  Complete $192,000
 Fall 2016 Cope/Telecom Data Center   $493,411
 Spring 2017 Sam H. Ingram Building   $191,000
 Spring 2017 Honors Building   $249,000
 Spring 2017 Cope Administration Bulding (partial upgrade)   $25,000
 

TOTAL FY2017

 

$ 1,352,411

       

 

 Projected Upgrades for FY2018

 

 

Date of Upgrade Building Status cost
  Business and Aerospace   $1,252,000
  Cason-Kennedy Nursing Building   $546,000
  Voorhies Engineering Technology   $188,000
  College of Education   $618,000
  Keathley University Center (KUC)   $715,400
  Peck Hall   $710,000
  Saunders Fine Art   $133,000
  TOTAL FY2018   $ 4,162,400
       

 

Projected Upgrades for FY2019

   
Date of Upgrade Building Status cost
  Fairview Building   $270,000
  Ellington Human Sciences   $110,000
  Todd Hall   $283,000
  Ned McWherter Learning Resources Center   $253,000
  Bragg Mass Comm Building   $277,000
  James Union Building   $116,000
  Stark Agribusiness   $32,000
  Wood-Stegall Center   $19,768
  Jean A. Jack Flight Center   $20,000
  Forrest Hall   $249,000
  Wright Music Building   $209,000
  ROTC Annex   $49,000
  Holmes Maintenance Complex   $65,000
  Printing Services Building   $62,000
  Student Recreation Center   $160,000
  Tenn Center for the Study and Treatment of Dyslexia   $30,000
  Tom H. Jackson Building   $72,000
  Campus Police Building   $17,500
  Alumni Office   $10,540
  Alumni Relations House   $10,540
  The Chris Young Cafe   $5,200
  1114 East Lytle Street   $6,500
  1416 East Main Street (Historice Preservation)   $5,200
  1417 East Main Street (Center ofr Historic Preservation)   $15,300
  211 College Heights   $21,000
  Central Utility Plant   $57,000
  Emmett and Rose K   $33,000
  Greenhouse   $12,900
  Horticulture Facility   $52,000
  Housing Maintenance Annex   $112,000
  Maintenance Complex - Bayer Travis   $15,000
  Maintenance Complex Hastings   $21,000
  Maintenance Complex Haynes-Turner   $122,800
  Maintenance Complex Open Shed   $56,000
  Maintenance Complex Warehouse (unrenovated area)   $37,000
  Observatory   $14,900
  Parking Services   $93,200
  President's Home   $26,400
  ProjectHELP   $19,000
  TOTAL FY2019    $ 3,040,748
       

 

Projected Upgrades for FY2020

   
Date of Upgrade Building Status cost
  Miller Coliseum   $890,900
  Satellite Chiller Plant   $27,900
  Storage Warehouse   $45,400
  Telecomm Building   $124,000
  Tennessee Livestock   $127,400
  Vocational Agriculture   $6,500
  Farm Shop (Guy James)   $32,000
  Miller Lanier Airway Science   $48,900
  Pittard Campus School (C/O Rutherford Cty Schools)   $0
  James E. Walker Library   $795,000
  Student Union   $695,000
  TOTAL FY2020   $ 2,793,000
       

 

Projected Upgrades for FY2021

   
Date of Upgrade Building Status cost
  Airport Hangar 2   $37,900
  Donald McDonald Hangar   $46,300
  Jones Hall   $239,000
  Main Dairy Farm (Guy James)   $22,900
  Natatorium   $0
  Telescope Building   $19,900
  Recreation Storage   $22,900
  Champion Way Garage   $22,900
  MTSU Blvd Garage (installed 2014)   $37,546
  Science Building (installed 2014)   $1,214,000
  Student Services (installed 2014)   $293,713
  Campus Core Routing   $628,800
  Campus Egress Routing   $145,000
  TOTAL FY2021   $ 2,730,859
       
   

Projected Upgrades for FY2022

   
Date of Upgrade Building Status cost
  Airport Flight Simulator Building   $20,000
  Bell Street Center   $415,000
  McFarland Building   $60,000
  Kirksey Old Main (KOM)   $750,000
  Midgett Building (cost included in KOM)   $0
  TOTAL FY2022   $ 1,245,000
       
 

Athletics

 

$816,100

       

 

Projected Upgrades for FY2017

   
Date of Upgrade Building Status cost
  Baseball Stadium   $249,900
  TOTAL FY2017   $ 249,900
       

 

Projected Upgrades for FY2018

   
Date of Upgrade Building Status cost
  Floyd Stadium   $222,000
  TOTAL FY2018   $ 222,000
       

 

Projected Upgrades for FY2019

   
Date of Upgrade Building Status cost
  Murphy Center   $239,000
  TOTAL FY2019   $ 239,000
       

 

Projected Upgrades for FY2020

   
Date of Upgrade Building Status cost
  Women's Softball Complex   $5,300
  Dean A Hayes Track and Soccer Stadium   $5,300
  Sports Medicine / Stadium Addition   $67,800
  Stephen B Smith Clubhouse and Indoor Training Facility   $23,000
  Tennis Shelter   $3,600
  TOTAL FY2020   $ 105,000
       
       
 

Housing

 

$2,816,320

       

 

Projected Upgrades for FY2017

   
Date of Upgrade Building Status cost
  Womack Lane Apartments - including Central Svcs   $195,000
  Beasley Hall   $45,452
  Deere Hall   $56,402
  Nicks Hall (cost included in Deere Hall)   $0
  Gracy Hall   $45,452
  Judd Hall   $45,452
  Rutledge Hall   $42,652
  TOTAL FY2017   $ 430,410
       

 

Projected Upgrades for FY2018

   
Date of Upgrade Building Status cost
  Corlew Hall   $699,000
  TOTAL FY2018   $ 699,000
       

 

Projected Upgrades for FY2019

   
Date of Upgrade Building Status cost
  Jim Cummings Hall   $699,000
  TOTAL FY2019   $ 699,000
       

 

Projected Upgrades for FY2020

   
Date of Upgrade Building Status cost
  Lyon Hall   $249,000
  Mary Hall (cost included in Lyon Hall)   $0
  McHenry Hall (cost included in Lyon Hall)   $0
  Scarlett Commons Complex   $95,685
  Smith Hall   $162,692
  TOTAL FY2020   $ 507,377
       

 

Projected Upgrades for FY2021

   
Date of Upgrade Building Status cost
  Monohan Hall   $249,000
  Reynolds Hall (included in Monohan Hall)   $0
  Schardt Hall (cost included in Monohan)   $0
  Sims Hall   $45,452
  Alpha Delta Pi House   $19,600
  Alpha Omicron Pi House   $19,600
  Chi Omega House   $19,600
  Kappa Alpha House   $19,600
  Sigma Alpha Epsilon House   $19,600
  Sigma Chi House   $19,600
  Sigma Nu House   $19,600
  TOTAL FY2021   $ 480,533

 

ITD Help Desk

Sun: 2:00pm – 9:00pm
Mon-Thur: 7:00am – 9:00pm
Fri: 7:00am – 4:30pm
Sat: 8:00am – 4:00pm


(615) 898-5345
help@mtsu.edu
Submit Work Order


The ITD Help Desk is located in KUC 320.


Dell University Store